Hole 9 is getting into its final stages of construction. This week, drainage was installed in all bunkers. Monday we will be getting a final approval from the architect and plan on installing the liners Wednesday 5/7. Sand will be added a few days later following the liner installation, and sod is planned to be installed 5/13.